Risk Mitigation Techniques – Guarantees, Insurance & Hedging
Risk cannot be eliminated in project finance - but it can be mitigated, transferred, or shared through various mechanisms.
Risk Mitigation Framework
Loading diagram…
1. Guarantees
A. Performance Guarantees (by EPC Contractor)
Purpose: Ensure contractor completes project as per specifications.
Types:
1. Bank Guarantee (BG) for Advance Payment:
- Value: 10-20% of contract value
- Example: EPC contract = ₹500 crore, BG = ₹50 crore
- Purpose: If contractor abandons project, SPV can invoke BG
2. Performance Bank Guarantee:
- Value: 5-10% of contract value
- Valid till project completion + defects liability period
- Example: ₹25 crore BG valid for 4 years
3. Technical Performance Guarantee:
- Contractor guarantees specific performance parameters
- Example - Solar Plant:
- Guaranteed CUF (Capacity Utilization Factor): 18%
- Actual CUF: 16%
- Penalty: ₹2 crore per 1% shortfall = ₹4 crore payable by contractor
B. Government/Sponsor Guarantees
1. Completion Guarantee (by Sponsors):
- Sponsors guarantee to complete the project
- If cost overrun, sponsors inject additional equity
- Required by lenders for greenfield projects
2. Viability Gap Funding (VGF) - by Government:
- Government provides upfront grant (up to 40% of project cost)
- Makes otherwise unviable projects bankable
- Example: Metro rail projects
3. Minimum Revenue Guarantee - by Government:
- Government guarantees minimum traffic/revenue
- Example: "Government will compensate if toll revenue < 90% of projected"
4. Subordinated Debt/Quasi-Equity - by Sponsors:
- Sponsors provide subordinated loan (ranks after senior debt)
- Absorbs first losses
- Comfort to senior lenders
C. Off-taker Guarantees
Power Purchase Agreement (PPA) - by DISCOM/Government:
- Guaranteed offtake of power for 25 years
- Fixed tariff or formula-based tariff
- Two-part tariff:
- Capacity Charge: Paid even if power not taken (fixed cost recovery)
- Energy Charge: Paid per unit consumed (variable cost recovery)
Take or Pay Contract:
- Buyer must pay even if doesn't take the product
- Common in gas pipelines, petrochemicals
2. Insurance
Projects use 10-15 different insurance policies. Key ones:
A. Construction Phase Insurance
1. Contractors All Risk (CAR) Insurance
Coverage:
- Damage to works under construction
- Perils: Fire, flood, earthquake, cyclone, theft, riots
- Third-party liability
Sum Insured: Full replacement cost of works Premium: 0.2-0.5% of sum insured Example: ₹1,000 crore project → ₹2-5 crore annual premium
2. Erection All Risk (EAR) Insurance
For projects involving machinery erection (power plants, factories):
- Covers equipment damage during erection
- Testing and commissioning coverage
3. Marine Cargo Insurance
- For imported equipment during shipping
- Coverage: Port-to-site
4. Third-Party Liability Insurance
- Covers injury/death to third parties
- Property damage to neighbors
- Example: Crane falls on neighboring building - insurance pays
B. Operational Phase Insurance
1. Property Insurance (Fire & Allied Perils)
- Covers damage to project assets post-completion
- Perils: Fire, explosion, natural disasters
- Sum Insured: Replacement value of assets
2. Business Interruption (BI) Insurance
- Covers loss of revenue if project cannot operate due to insured peril
- Example:
- Fire damages solar plant, 6 months to repair
- Lost revenue: ₹30 crore
- Insurance pays ₹30 crore
Indemnity Period: 6-24 months
3. Machinery Breakdown Insurance
- Covers sudden/accidental breakdown of machinery
- Example: Turbine rotor damage → ₹10 crore repair cost
4. Terrorism & Political Violence Insurance
- Covers damage from terrorism, war, civil commotion
- High-risk areas: ₹2-5 crore premium for ₹500 crore asset value (vs ₹2-3 lakh in normal property insurance)
5. Directors & Officers (D&O) Liability Insurance
- Protects directors from personal liability for company decisions
C. Political Risk Insurance (PRI)
Covered earlier - MIGA, ECAs, private insurers.
Coverage:
- Expropriation
- Currency inconvertibility
- War & political violence
- Breach of contract by government
D. Environmental Liability Insurance
- Covers costs of pollution cleanup
- Third-party claims for environmental damage
- Example: Chemical spill damages farmland → ₹20 crore compensation
3. Hedging Instruments
A. Interest Rate Hedging
1. Interest Rate Swap (IRS):
Mechanism:
- SPV pays fixed rate to bank
- Bank pays floating rate (MCLR+spread) to SPV
- Net effect: SPV has fixed-rate debt
Example:
Loan: ₹700 crore at MCLR + 2.5% (floating)
Current MCLR: 7.5% → Total: 10%
IRS: SPV pays 9.5% fixed, receives MCLR+2.5%
Net Interest Cost: 9.5% (fixed for 10-15 years)
If MCLR rises to 9%, SPV still pays 9.5%
If MCLR falls to 6%, SPV still pays 9.5%
Cost: Embedded in fixed rate (typically 0.5-1% higher than current floating)
2. Interest Rate Cap:
- Option to cap interest rate at (say) 12%
- If market rate > 12%, option seller pays the difference
- Example:
- Floating rate: MCLR + 2.5% = 13%
- Cap rate: 12%
- Bank pays SPV: 1% of ₹700 crore = ₹7 crore
Cost: Upfront premium = 0.5-1% of loan amount (₹3.5-7 crore)
When to Use: If uncertain about interest rate direction but want protection against spike
B. Foreign Exchange Hedging
1. Forward Contract:
- Lock in exchange rate for future date
- Example:
- USD 10 million payment due in 12 months
- Current rate: ₹82/USD
- 12-month forward rate: ₹83.50/USD
- Book forward → Pay ₹83.50 crore after 12 months (certainty!)
Cost: Forward premium/discount (~1-3% p.a.)
2. Currency Option:
- Right (not obligation) to buy/sell USD at fixed rate
- Example:
- Buy USD Call Option at ₹84/USD
- If spot rate in 12 months = ₹88/USD → Exercise option, buy at ₹84 (save ₹4)
- If spot rate = ₹80/USD → Don't exercise, buy at ₹80 (better rate)
Cost: Premium (2-4% of notional)
3. Cross-Currency Swap:
- Swap USD debt into INR debt
- Converts currency and interest rate exposure
C. Commodity Price Hedging
For projects exposed to commodity prices (oil, coal, metals):
1. Futures Contracts:
- Lock in price for future delivery
- Example: Coal plant locks coal price at ₹2,500/ton for next 2 years
2. Price Collar:
- Buy price floor + Sell price ceiling
- Example: Coal price range ₹2,000-3,000/ton
- If market < ₹2,000 → Receive payment (floor protection)
- If market > ₹3,000 → Pay out (capped cost)
4. Contractual Risk Mitigation
A. EPC Contract Protections
1. Fixed-Price Lump-Sum Turnkey Contract:
- Contractor bears cost overrun risk
- SPV pays fixed ₹500 crore (regardless of actual cost)
2. Liquidated Damages (LD):
- Pre-agreed penalty for delays/defects
- Typical: 0.5% of contract value per week of delay
- Cap: 10% of contract value
- Example: 20 weeks delay → ₹50 crore penalty
3. Performance Guarantees:
- Guaranteed plant output, efficiency, availability
- Shortfall → Financial compensation
4. Defects Liability Period (DLP):
- 12-24 months post-completion
- Contractor fixes all defects at no cost
B. O&M Contract Protections
1. Performance-Based Payment:
- Pay based on actual availability/performance
- Example: ₹10 crore/year base + ₹5 crore bonus if availability > 95%
2. Step-in Rights for Lenders:
- If O&M contractor fails, lenders can appoint replacement
C. Concession Agreement Protections
1. Change in Law Clause:
- If law/regulation changes adversely, government compensates or extends concession period
2. Force Majeure Clause:
- Excuses performance during events beyond control (earthquake, war)
- Relief: Extension of time, cost compensation
3. Termination Payments:
- If government terminates early, must pay:
- Outstanding debt + equity (with reasonable return)
- OR Fair market value
5. Credit Enhancement
A. Debt Service Reserve Account (DSRA)
- Cash reserve = 6-12 months of debt service
- Example: If annual debt service = ₹120 crore, DSRA = ₹60 crore
- Acts as buffer if cash flow shortage
B. Escrow Account
- All project revenues flow into escrow account
- Lenders control disbursements (waterfall mechanism)
- Prevents sponsors from siphoning cash
C. Senior vs Subordinated Debt
- Senior Debt: First claim on assets and cash flows (70-80% of debt)
- Subordinated Debt: Second claim, absorbs losses before senior (10-20% of debt, provided by sponsors or DFIs)
Risk Mitigation Cost Summary
| Technique | Typical Cost |
|---|---|
| Performance Bank Guarantee | 1-2% p.a. of BG amount |
| CAR/EAR Insurance | 0.2-0.5% of project cost |
| Property & BI Insurance | 0.1-0.3% of asset value |
| Political Risk Insurance | 1-5% p.a. (country dependent) |
| Interest Rate Swap | 0.5-1% higher fixed rate |
| Forex Forward | 1-3% p.a. forward premium |
| TOTAL Risk Mitigation Cost | 2-5% of project cost |
Example: ₹1,000 crore project → ₹20-50 crore total mitigation cost over project life
Summary
- Risk mitigation is achieved through Guarantees, Insurance, Hedging, and Contracts
- Guarantees: Performance (EPC), Completion (Sponsor), Revenue (Government), Off-take (PPA)
- Insurance: CAR, Property, Business Interruption, Political Risk, Terrorism
- Hedging: Interest Rate Swaps/Caps, Forex Forwards, Commodity Futures
- Contractual: Fixed-price EPC, Liquidated Damages, Change-in-Law clause
- Credit Enhancement: DSRA, Escrow, Subordinated Debt
- Total cost: 2-5% of project cost (necessary to make project bankable!)
Quiz Time! 🎯
Loading quiz…
Next Chapter: Project Financing Methods – Equity, Debt & Hybrid Structures! 💰