Home > Topics > Project Finance > Project Management – Planning, Monitoring & Execution

Project Management – Planning, Monitoring & Execution

Successful project management is the key to delivering infrastructure projects on time, within budget, and to quality standards. This involves systematic planning, continuous monitoring, and effective execution.


The Three Pillars of Project Management

Loading diagram…

Continuous Loop
These three activities (Planning, Execution, Monitoring & Control) run continuously throughout the project lifecycle with constant feedback loops.

1. Project Planning

Planning is the most critical phase - "Failing to plan is planning to fail."

Key Planning Activities

A. Work Breakdown Structure (WBS)

  • Break down the project into smaller, manageable tasks
  • Create a hierarchical structure of deliverables
  • Assign responsibilities for each task

Example for a Power Plant:

Loading diagram…

B. Resource Planning

  • Manpower: Engineers, laborers, supervisors
  • Materials: Cement, steel, equipment
  • Machinery: Cranes, excavators, trucks
  • Money: Cash flow requirements

C. Time Planning (Scheduling)

Three main scheduling techniques:

1. Gantt Chart

  • Visual timeline showing start and end dates of tasks
  • Shows task dependencies
  • Easy to understand
  • Limitation: Doesn't show critical path

2. PERT (Program Evaluation and Review Technique)

  • Network diagram showing task dependencies
  • Uses three time estimates:
    • Optimistic Time (O) - Best case
    • Most Likely Time (M) - Normal case
    • Pessimistic Time (P) - Worst case
  • Expected Time = (O + 4M + P) / 6
  • Good for projects with high uncertainty

3. CPM (Critical Path Method)

  • Network diagram showing task dependencies
  • Identifies the Critical Path - longest sequence of tasks
  • Any delay in critical path tasks delays the entire project
  • Helps prioritize monitoring efforts
  • Most widely used in construction projects
Critical Path
Tasks on the critical path have zero slack - they cannot be delayed without delaying the entire project. Non-critical tasks have some slack time.

D. Cost Planning (Budgeting)

  • Prepare detailed cost estimates for each WBS element
  • Create cashflow projections (monthly/quarterly)
  • Build in contingency (5-10% for construction, 15-20% for new technology)
  • Monitor Cost-to-Complete throughout execution

E. Risk Planning

  • Identify all project risks
  • Assess probability and impact
  • Develop mitigation strategies
  • Allocate risks to appropriate parties (via contracts)
  • Create risk register

2. Project Execution

Execution is where planning meets reality. This phase involves:

Key Execution Activities

A. Resource Mobilization

  • Move equipment to site
  • Hire and deploy manpower
  • Procure materials
  • Set up site offices and utilities

B. Contract Management

  • Administer EPC contract
  • Process change orders
  • Manage contractor performance
  • Resolve disputes

C. Procurement Management

  • Issue purchase orders
  • Track deliveries
  • Inspect quality of materials/equipment
  • Manage inventory

D. Quality Management

  • Implement Quality Assurance (QA) plan
  • Conduct Quality Control (QC) checks
  • Document certifications
  • Conduct audits

E. Communication Management

  • Regular meetings with stakeholders
  • Monthly progress reports
  • Issue management dashboards
  • Escalation procedures

3. Project Monitoring & Control

Continuous monitoring ensures that the project stays on track.

Key Monitoring Tools

A. Progress Monitoring

Physical Progress:

  • Site inspections by Independent Engineer
  • Milestone completion tracking
  • Photographs and videos
  • Weighting System: Each milestone assigned a weight; overall % completion calculated

Example for Highway Project:

MilestoneWeightStatus
Land acquisition10%Complete
Site clearance5%Complete
Earthwork25%80% done
Drainage10%Not started
Pavement30%Not started
Structures (bridges)15%50% done
Signage5%Not started

Overall Progress = (10% × 100%) + (5% × 100%) + (25% × 80%) + (15% × 50%) = 35%

B. Cost Monitoring

Earned Value Management (EVM) - Most sophisticated method:

  • Planned Value (PV): Budgeted cost of work scheduled
  • Earned Value (EV): Budgeted cost of work performed
  • Actual Cost (AC): Actual cost of work performed

Key Metrics:

  • Cost Variance (CV) = EV - AC (Positive = Under budget)
  • Schedule Variance (SV) = EV - PV (Positive = Ahead of schedule)
  • Cost Performance Index (CPI) = EV / AC (>1 = Good, <1 = Cost overrun)
  • Schedule Performance Index (SPI) = EV / PV (>1 = Ahead, <1 = Delayed)
EVM Power
EVM allows you to predict final project cost and completion date based on current performance - critical for lenders!

C. Quality Monitoring

  • Regular inspections by QC team
  • Material testing (concrete strength, steel quality, etc.)
  • Compliance with specifications
  • Non-Conformance Reports (NCRs)

D. Risk Monitoring

  • Track identified risks
  • Update probability/impact as new information emerges
  • Monitor risk mitigation measures
  • Identify new risks

4. Project Control

When monitoring reveals deviations, control actions are needed:

Control Measures

For Time Delays

  • Fast-tracking: Overlap activities (e.g., start equipment installation before civil work fully complete)
  • Crashing: Add resources to critical path tasks
  • Resequencing: Change order of activities
  • Work shifts: Implement 24-hour shifts

For Cost Overruns

  • Value engineering: Find cost-effective alternatives
  • Scope reduction: Eliminate non-essential features
  • Better negotiation: Renegotiate supplier/contractor rates
  • Additional funding: Inject more equity or subordinated debt

For Quality Issues

  • Rework: Redo the defective work
  • Root cause analysis: Prevent recurrence
  • Contractor penalties: As per contract
  • Change contractor: As last resort (rarely done due to delays)

Reporting to Stakeholders

Monthly Progress Report (MPR)

Submitted to lenders, contains:

  1. Executive Summary: Overall status (Red/Amber/Green)
  2. Physical Progress: % completion vs planned
  3. Financial Progress: Funds disbursed vs budget
  4. Key Milestones: Achieved in month
  5. Issues & Delays: Problems faced
  6. Corrective Actions: Steps taken
  7. Forecast: Revised completion date and cost

Dashboard Indicators

IndicatorStatus
Schedule🟢 On track
Cost🟡 5% overrun
Quality🟢 No NCRs
Safety🟢 No accidents
Environment🟡 1 minor violation

Key Performance Indicators (KPIs)

Construction Phase KPIs

  1. Schedule Performance Index (SPI): Should be >0.95
  2. Cost Performance Index (CPI): Should be >0.95
  3. Safety Incident Rate: Aim for zero Lost Time Injuries (LTIs)
  4. Quality Defect Rate: <2%
  5. Payment Cycle: <30 days for contractor payments

Operational Phase KPIs

  1. Plant Availability: >95% for power plants
  2. Traffic: Actual vs projected traffic (for roads)
  3. Debt Service Coverage Ratio (DSCR): >1.3
  4. Operational Expenses: Within budget

Project Management Software

Modern projects use specialized software:

  • MS Project: Most common for planning and Gantt charts
  • Primavera P6: Industry standard for large infrastructure (CPM, resource management)
  • Procore: Construction management platform
  • SAP: For cost and procurement management
  • Custom Dashboards: Using Power BI or Tableau

Summary

  • Project Management has three pillars: Planning, Execution, and Monitoring
  • Planning tools: WBS, Gantt Chart, PERT, CPM, Risk Register
  • Critical Path identifies tasks that can't be delayed
  • Earned Value Management (EVM) is the best method for cost/schedule monitoring
  • Key metrics: SPI, CPI, DSCR
  • Monthly Progress Reports keep lenders informed
  • Modern projects use software like Primavera P6 and MS Project
  • Control actions (fast-tracking, crashing) correct deviations

Quiz Time! 🎯

Loading quiz…


Next Chapter: Valuing a Project – Approaches & Cash Flow Concepts! 💰