Home > Topics > Project Finance > Project Development – Phases & Stakeholders

Project Development – Phases & Stakeholders

Every major infrastructure project goes through a well-defined development lifecycle from initial idea to full commercial operation. Understanding these phases and the stakeholders involved is crucial for successful project execution.


Project Development Lifecycle

Loading diagram…


Phase 1: Project Identification

Activities

  • Identify infrastructure gap or market opportunity
  • Define project objective and scope
  • Conduct preliminary market assessment
  • Evaluate strategic fit with company/government goals

Key Stakeholders

  • Sponsors/Developers
  • Government (for PPP projects)
  • Sector experts

Duration

1-3 months


Phase 2: Pre-Feasibility Study

Activities

  • Preliminary technical assessment
  • Site reconnaissance
  • Initial cost estimates (±30% accuracy)
  • Regulatory framework review
  • Alternative options analysis

Deliverables

  • Pre-feasibility Report
  • Rough financial projections
  • Go/No-go recommendation

Duration

2-4 months

Critical Decision Point
Many projects are abandoned at this stage if preliminarynumbers don't work or regulatory hurdles appear insurmountable.

Phase 3: Detailed Feasibility Study

This is the most critical phase where the project is evaluated in detail.

3A. Technical Feasibility

  • Detailed engineering design
  • Technology selection
  • Site investigation and surveys
  • Environmental Impact Assessment (EIA)
  • Procurement strategy

3B. Economic Feasibility

  • Demand analysis and traffic/revenue projections
  • Economic Cost-Benefit Analysis
  • Macro-economic impact assessment
  • Alternative analysis

3C. Financial Feasibility

  • Detailed financial model (20-25 year projections)
  • Sources and Uses of Funds
  • Financial metrics (Project IRR, Equity IRR, DSCR)
  • Sensitivity analysis
  • Bankability assessment

3D. Legal & Regulatory Feasibility

  • Land acquisition requirements
  • Required permits and clearances (15-25 different clearances)
  • Regulatory approvals timeline
  • Contractual framework

Deliverables

  • Detailed Project Report (DPR) - 500-1000 pages
  • Financial Model
  • EIA Report
  • Market Study

Duration

6-12 months


Phase 4: Structuring & Procurement

Activities

Legal Structuring:

  • Create SPV (Special Purpose Vehicle)
  • Finalize shareholder agreement
  • Determine debt-equity ratio

Financing Strategy:

  • Identify potential lenders
  • Prepare Information Memorandum
  • Approach institutional investors
  • Structure security package

Procurement:

  • EPC contractor selection (through competitive bidding or negotiation)
  • O&M contractor selection
  • Equipment supplier selection

Contract Negotiation:

  • Concession Agreement (with Government)
  • EPC Contract
  • O&M Agreement
  • Off-take Agreement

Key Advisors Engaged

  • Financial Advisor
  • Legal Advisors (for each party)
  • Technical Advisor
  • Insurance Advisor

Duration

8-18 months

Time-consuming but critical
This phase determines the entire risk allocation framework for the project.

Phase 5: Financial Close

Financial Close is the date when all project documents are signed and conditions precedent are satisfied, allowing funds to be drawn.

Pre-conditions for Financial Close

  1. ✅ All permits and clearances obtained
  2. ✅ SPV incorporated
  3. ✅ Land acquired
  4. ✅ All project agreements signed
  5. ✅ Security documents executed
  6. ✅ Conditions precedent in Loan Agreement satisfied
  7. ✅ Equity funded into SPV account

Documents Signed (20-30 agreements)

  1. Loan Agreement
  2. Security Documents (Mortgage, Pledge, Assignment)
  3. EPC Contract
  4. O&M Agreement
  5. Concession Agreement
  6. Escrow Agreement
  7. Direct Agreements (Lenders' step-in rights)
  8. Shareholder Agreement
  9. Insurance Policies

Celebration Moment

Financial Close is a major milestone celebrated by all parties - it's the "point of no return" where the project becomes a reality.


Phase 6: Construction

Activities

  • Site mobilization
  • Construction as per approved design
  • Monthly progress monitoring by Independent Engineer
  • Disbursement of loans linked to construction progress
  • Change management (variations to design)

Key Stakeholders

  • EPC Contractor (main responsibility)
  • Independent Engineer (monitors for lenders)
  • SPV (coordination)
  • Lenders (fund disbursement)

Duration

2-5 years (depending on project type)

Risk

Construction Risk is the highest risk period:

  • Cost overruns
  • Time delays
  • Technical failures
  • Force majeure events
Lender Protection
Lenders protect themselves through Independent Engineer monitoring, performance guarantees from contractors, and Liquidated Damages clauses.

Phase 7: Commissioning & Testing

Activities

  • Mechanical completion certification
  • Performance testing
  • Provisional Acceptance
  • Training of O&M staff
  • Final Acceptance (after defect-free period)

Duration

3-6 months


Phase 8: Commercial Operation

Activities

  • Revenue generation begins
  • Debt servicing starts
  • Regular O&M activities
  • Monitoring by lenders (DSCR, coverage ratios)
  • Dividend distribution (after debt service)

Duration

15-25 years (concession period)


Key Stakeholders in Project Development

1. Sponsors

Role: Initiate project, provide equity, manage execution

Examples: Tata Power, Reliance, Adani, L&T

2. Government

Role: Grantor of concession, regulator, sometimes off-taker

Examples: NHAI, Ministry of Power, State Governments

3. Lenders

Role: Provide debt financing (60-80% of project cost)

Types:

  • Commercial Banks
  • Development Finance Institutions
  • Export Credit Agencies
  • Institutional Investors

4. Contractors

Role: Design and build the project

Key Contract: EPC Contract (Engineering, Procurement, Construction)

Examples: L&T, Shapoorji Pallonji, GE, Siemens

5. Operators

Role: Operate and maintain the project post-construction

Key Contract: O&M Agreement

6. Off-takers

Role: Purchase project output (power, tolls, etc.)

Examples: State Electricity Boards, NHAI (for toll roads)

7. Advisors

  • Financial Advisors
  • Legal Advisors
  • Technical Advisors
  • Environmental Advisors
  • Insurance Advisors

8. Regulators

Role: Issue permits, monitor compliance

Examples: Pollution Control Board, Forest Department, Ministry of Environment


Timeline Summary

PhaseDuration
Identification1-3 months
Pre-Feasibility2-4 months
Detailed Feasibility6-12 months
Structuring & Procurement8-18 months
Total: Concept to Financial Close18-36 months
Construction2-5 years
Total: Concept to COD (Commercial Operation Date)3-8 years
Long Journey
From initial idea to revenue generation, a large infrastructure project takes 3-8 years. Patient capital and strong project management are essential.

Summary

  • Project development follows 8 distinct phases from identification to operation
  • Detailed Feasibility Study (Phase 3) is the most critical - determines project viability
  • Financial Close (Phase 5) is a major milestone when all documents are signed
  • Construction (Phase 6) carries the highest risk
  • Key stakeholders: Sponsors, Government, Lenders, Contractors, Operators, Off-takers, Advisors
  • Timeline from concept to operation: 3-8 years
  • Each phase has specific deliverables and decision points

Quiz Time! 🎯

Loading quiz…


Next Chapter: Project Management - Planning, Monitoring & Execution! 📊