Legal Aspects of Project Finance – Key Agreements & Compliance
Project finance involves 20-30 legal agreements creating a complex web of rights and obligations. Understanding these is critical.
Key Project Agreements
Loading diagram…
1. Concession Agreement
Parties: SPV (Concessionaire) and Government (Grantor)
Key Terms:
- Concession Period: 20-30 years
- Scope of Work: What must be built/operated
- Revenue Rights: Toll collection, tariff
- Land: Government provides land
- Force Majeure: Events beyond control
- Termination: Conditions and compensation
Example Clause - Termination Payment:
- If government terminates: Pay debt outstanding + equity with 15% return
- If SPV defaults: Government takes over, pays only debt
2. EPC Contract (Engineering, Procurement, Construction)
Parties: SPV and EPC Contractor
Key Provisions:
- Fixed Price Lump Sum: ₹500 crore (contractor bears cost overrun)
- Completion Date: 24 months
- Liquidated Damages: 0.5% per week delay (max 10%)
- Performance Guarantee: 10% bank guarantee
- Defects Liability: 12-24 months post-completion
3. Loan Agreement
Parties: SPV and Lenders
Key Terms:
- Loan Amount: ₹700 crore
- Interest: MCLR + 2.5%
- Repayment: 15 years
- Security: First charge on all assets
- Covenants: Financial and operational restrictions (covered in next chapter)
4. Power Purchase Agreement (PPA) / Off-take Agreement
Parties: SPV and Buyer (DISCOM for power, NHAI for toll roads)
Key Terms:
- Tenure: 25 years
- Tariff: Fixed or formula-based
- Capacity/Volume: Committed offtake
- Payment Terms: Within 30 days of billing
"Take or Pay" clause: Buyer must pay even if doesn't take supply
5. Direct Agreements
Lenders' Step-In Rights:
- Lenders sign direct agreements with EPC contractor, O&M contractor, government
- Purpose: If SPV defaults, lenders can step in and appoint new management
Regulatory Compliance
Approvals Required
- Incorporation (ROC - Registrar of Companies)
- Environmental Clearance (Ministry of Environment)
- Forest Clearance (if forest land involved)
- Water/Pollution NOCs
- FIPB approval (if foreign investment)
- SEBI (if issuing bonds)
- RBI (if ECB)
Dispute Resolution
Hierarchy
1. Negotiation (30-60 days) 2. Mediation (facilitated settlement) 3. Arbitration (binding decision by arbitrator) 4. Litigation (courts - avoid if possible!)
Arbitration is Preferred:
- Faster (12-24 months vs 5-10 years for courts)
- Confidential
- Expert arbitrators
- Enforceable globally (New York Convention)
Arbitration Clause Example:
- Seat: Singapore/London
- Rules: SIAC/LCIA
- Language: English
- Number of Arbitrators: 3
Summary
- Projects have 20-30 agreements (Concession, EPC, Loan, PPA, etc.)
- Concession Agreement defines overall project rights
- EPC Contract allocates construction risk
- Loan Agreement has security and covenants
- Direct Agreements give lenders step-in rights
- Arbitration preferred over litigation
Quiz Time! 🎯
Loading quiz…
Next Chapter: Project Finance Loan Documentation! 📄