Home > Topics > Project Finance > Legal Aspects of Project Finance – Key Agreements & Compliance

Legal Aspects of Project Finance – Key Agreements & Compliance

Project finance involves 20-30 legal agreements creating a complex web of rights and obligations. Understanding these is critical.


Key Project Agreements

Loading diagram…


1. Concession Agreement

Parties: SPV (Concessionaire) and Government (Grantor)

Key Terms:

  • Concession Period: 20-30 years
  • Scope of Work: What must be built/operated
  • Revenue Rights: Toll collection, tariff
  • Land: Government provides land
  • Force Majeure: Events beyond control
  • Termination: Conditions and compensation

Example Clause - Termination Payment:

  • If government terminates: Pay debt outstanding + equity with 15% return
  • If SPV defaults: Government takes over, pays only debt

2. EPC Contract (Engineering, Procurement, Construction)

Parties: SPV and EPC Contractor

Key Provisions:

  • Fixed Price Lump Sum: ₹500 crore (contractor bears cost overrun)
  • Completion Date: 24 months
  • Liquidated Damages: 0.5% per week delay (max 10%)
  • Performance Guarantee: 10% bank guarantee
  • Defects Liability: 12-24 months post-completion

3. Loan Agreement

Parties: SPV and Lenders

Key Terms:

  • Loan Amount: ₹700 crore
  • Interest: MCLR + 2.5%
  • Repayment: 15 years
  • Security: First charge on all assets
  • Covenants: Financial and operational restrictions (covered in next chapter)

4. Power Purchase Agreement (PPA) / Off-take Agreement

Parties: SPV and Buyer (DISCOM for power, NHAI for toll roads)

Key Terms:

  • Tenure: 25 years
  • Tariff: Fixed or formula-based
  • Capacity/Volume: Committed offtake
  • Payment Terms: Within 30 days of billing

"Take or Pay" clause: Buyer must pay even if doesn't take supply


5. Direct Agreements

Lenders' Step-In Rights:

  • Lenders sign direct agreements with EPC contractor, O&M contractor, government
  • Purpose: If SPV defaults, lenders can step in and appoint new management

Regulatory Compliance

Approvals Required

  1. Incorporation (ROC - Registrar of Companies)
  2. Environmental Clearance (Ministry of Environment)
  3. Forest Clearance (if forest land involved)
  4. Water/Pollution NOCs
  5. FIPB approval (if foreign investment)
  6. SEBI (if issuing bonds)
  7. RBI (if ECB)

Dispute Resolution

Hierarchy

1. Negotiation (30-60 days) 2. Mediation (facilitated settlement) 3. Arbitration (binding decision by arbitrator) 4. Litigation (courts - avoid if possible!)

Arbitration is Preferred:

  • Faster (12-24 months vs 5-10 years for courts)
  • Confidential
  • Expert arbitrators
  • Enforceable globally (New York Convention)

Arbitration Clause Example:

  • Seat: Singapore/London
  • Rules: SIAC/LCIA
  • Language: English
  • Number of Arbitrators: 3

Summary

  • Projects have 20-30 agreements (Concession, EPC, Loan, PPA, etc.)
  • Concession Agreement defines overall project rights
  • EPC Contract allocates construction risk
  • Loan Agreement has security and covenants
  • Direct Agreements give lenders step-in rights
  • Arbitration preferred over litigation

Quiz Time! 🎯

Loading quiz…


Next Chapter: Project Finance Loan Documentation! 📄